PEPSystems Alternative Soil Treatment

An intermediate oil and gas company asked Earthmaster to remediate over 9,000 m³ of hydrocarbon-impacted soil from emulsion spills. Due to the high trucking costs to the nearest Class 2 landfill, an alternative disposal method was needed.

Earthmaster proposed phytoremediation using PEPSystems®. Three regulator approved soil treatment facilities were set up near the contaminated sites. After spreading the soil to a depth of 0.40 m, it was conditioned, amended, and seeded with a PGPR-treated grass mix in late autumn.

In the first treatment year, plant growth was robust, achieving 100% ground cover. Soil tests showed a 65% reduction in F2 hydrocarbons and a 17% decrease in F3 levels. Based on results from similar sites, Alberta Tier 1 Criteria were met within three growing seasons. The project’s cost is forecast to be 30-40% lower than landfill disposal.

Status

Completed

  • PHC impacted soil stockpiled on-site.

  • Brush removal from the phytoremediation treatment pad area.

  • Surface soil & organic material stripped & stockpiled.

  • Clay is compacted in 0.15 m layers.

  • Hydraulic conductivity testing for ESRD compliance.

  • Impacted soil is spread to depth of 0.50 m.

  • Rototilling of impacted soil and fertilizer application.

  • Early summer plant growth across the treatment area.

  • Excellent plant growth across the treatment area.

  • Baling vegetation for removal from the treatment area.

  • Fall application of fertilizer to the treatment area.

  • Results from PHC impacted site northern BC.